SOUTH OFFSHORE was contracted for the installation of 2 I-tubes and a 27km subsea electrical cable between two platforms, in 100m depth. This project was located in Republique of Congo.
Scope Of Work:
Platforms Preparatory Works (Installation of Pull-in System on each platform)
Design / Fabrication & Installation of 2 I-tubes
Installation & Pre-commissioning of 27km subsea electrical cable between 2 platforms.
Execution Strategy:
Project management, Engineering, Procurement, Logistics, Onshore works, Offshore operations performed by South Offshore
Fabrication and subcontracted services
Sourcing and mobilization of an installation vessel
Management of interfaces and simultaneous operations
Project Key Facts:
Intervention on critical assets for CLIENT
Fast Track campaigns (6 months between Effective Date and Electrical cable start-up)
Diverless operations / Deployment of Patented Smart Clamp solution
40 000 man-hours, of which:
6,000 hours of engineering
3,000 hours of project management
5,000 hours of onshore preparation
No Defect, completion ahead of the Project Schedule and within Client’s critical path requirements