Description

SOUTH OFFSHORE was contracted for the Installation of 2 off jumpers, in 650 m depth. This project was located in Republique of Congo.
 

Scope Of Work:

  • Design / Fabrication & Test of the Spreader Bar
  • Preparation, Lifting Test and Onshore Lifiting of jumpers
  • Offshore Lifting, Installation & Pre-commissioning of Two jumpers.
 

Execution Strategy:

  • Project management, Engineering, Procurement, Logistics, Onshore works, Offshore operations performed by South-Offshore
  • Fabrication and subcontracted services
  • Sourcing and mobilization of an installation vessel
  • Management of interfaces and simultaneous operations
 

Project Key Facts:

  • Intervention on critical assets for CLIENT
  • Fast Track campaigns
  • 50 000 man-hours, of which:
    • 8,000 hours of engineering
    • 5,000 hours of project management
    • 5,000 hours of onshore preparation
  • No Defect, completion ahead of the Project Schedule and within Client’s critical path requirements